Review of mathematical models for production planning under uncertainty due to lack of homogeneity: proposal of a conceptual model

[EN] Lack of homogeneity in the product (LHP) appears in some production processes that confer heterogeneity in the characteristics of the products obtained. Supply chains with this issue have to classify the product in different homogeneous subsets, whose quantity is uncertain during the production...

Descripción completa

Detalles Bibliográficos
Autores: Mundi, I., Alemany Díaz, María Del Mar|||0000-0002-0992-8441, Poler, R.|||0000-0003-4475-6371, Fuertes-Miquel, Vicente S.|||0000-0003-3524-2555
Tipo de recurso: artículo
Fecha de publicación:2019
País:España
Institución:Universitat Politècnica de València (UPV)
Repositorio:RiuNet. Repositorio Institucional de la Universitat Politécnica de Valéncia
Idioma:inglés
OAI Identifier:oai:riunet.upv.es:10251/136500
Acceso en línea:https://riunet.upv.es/handle/10251/136500
Access Level:acceso abierto
Palabra clave:Planning
Optimisation
Production
Uncertainty
Mathematical modelling
ORGANIZACION DE EMPRESAS
MECANICA DE FLUIDOS
id ES_97d2b4ef2e520b147fff6d3aa31acc49
oai_identifier_str oai:riunet.upv.es:10251/136500
network_acronym_str ES
network_name_str España
repository_id_str
spelling Review of mathematical models for production planning under uncertainty due to lack of homogeneity: proposal of a conceptual modelMundi, I.Alemany Díaz, María Del Mar|||0000-0002-0992-8441Poler, R.|||0000-0003-4475-6371Fuertes-Miquel, Vicente S.|||0000-0003-3524-2555PlanningOptimisationProductionUncertaintyMathematical modellingORGANIZACION DE EMPRESASMECANICA DE FLUIDOS[EN] Lack of homogeneity in the product (LHP) appears in some production processes that confer heterogeneity in the characteristics of the products obtained. Supply chains with this issue have to classify the product in different homogeneous subsets, whose quantity is uncertain during the production planning process. This paper proposes a generic framework for reviewing in a unified way the literature about production planning models dealing with LHP uncertainty. This analysis allows the identification of similarities among sectors to transfer solutions between them and gaps existing in the literature for further research. The results of the review show: (1) sectors affected by LHP inherent uncertainty, (2) the inherent LHP uncertainty types modelled, and (3) the approaches for modelling LHP uncertainty most widely employed. Finally, we suggest a conceptual model reflecting the aspects to be considered when modelling the production planning in sectors with LHP in an uncertain environment.This research was initiated within the framework of the project funded by the Ministerio de Economía y Competitividad [Ref. DPI2011-23597] entitled ‘Methods and models for operations planning and order management in supply chains characterised by uncertainty in production due to the lack of product uniformity’ (PLANGES-FHP) already finished. After, the project leading to this application has received funding from the European Union’s research and innovation programme under the H2020 Marie Skłodowska-Curie Actions with the grant agreement No 691249, Project entitled ’Enhancing and implementing Knowledge based ICT solutions within high Riskand Uncertain Conditions for Agriculture Production Systems’ (RUC-APS).Taylor & FrancisDepartamento de Ingeniería Hidráulica y Medio AmbienteDepartamento de Organización de EmpresasCentro de Investigación en Gestión e Ingeniería de ProducciónEscuela Técnica Superior de Ingeniería IndustrialEscuela Politécnica Superior de AlcoyEuropean CommissionMinisterio de Ciencia e InnovaciónRepositorio Institucional de la Universitat Politècnica de València Riunet20192019-01-01journal articlehttp://purl.org/coar/resource_type/c_6501VoRhttp://purl.org/coar/version/c_970fb48d4fbd8a85info:eu-repo/semantics/articleapplication/pdfapplication/pdfhttps://riunet.upv.es/handle/10251/136500reponame:RiuNet. Repositorio Institucional de la Universitat Politécnica de Valénciainstname:Universitat Politècnica de València (UPV)InglésengEuropean Commission https://doi.org/10.13039/501100000780 H2020 691249 Enhancing and implementing Knowledge based ICT solutions within high Risk and Uncertain Conditions for Agriculture Production SystemsMinisterio de Ciencia e Innovación http://dx.doi.org/10.13039/501100004837 DPI2011-23597 METODOS Y MODELOS PARA LA PLANIFICACION DE OPERACIONES Y GESTION DE PEDIDOS EN CADENAS DE SUMINISTRO CARACTERIZADAS POR LA FALTA DE HOMOGENEIDAD EN EL PRODUCTOopen accesshttp://purl.org/coar/access_right/c_abf2Reserva de todos los derechoshttp://rightsstatements.org/vocab/InC/1.0/info:eu-repo/semantics/openAccessoai:riunet.upv.es:10251/1365002026-06-13T07:49:27Z
dc.title.none.fl_str_mv Review of mathematical models for production planning under uncertainty due to lack of homogeneity: proposal of a conceptual model
title Review of mathematical models for production planning under uncertainty due to lack of homogeneity: proposal of a conceptual model
spellingShingle Review of mathematical models for production planning under uncertainty due to lack of homogeneity: proposal of a conceptual model
Mundi, I.
Planning
Optimisation
Production
Uncertainty
Mathematical modelling
ORGANIZACION DE EMPRESAS
MECANICA DE FLUIDOS
title_short Review of mathematical models for production planning under uncertainty due to lack of homogeneity: proposal of a conceptual model
title_full Review of mathematical models for production planning under uncertainty due to lack of homogeneity: proposal of a conceptual model
title_fullStr Review of mathematical models for production planning under uncertainty due to lack of homogeneity: proposal of a conceptual model
title_full_unstemmed Review of mathematical models for production planning under uncertainty due to lack of homogeneity: proposal of a conceptual model
title_sort Review of mathematical models for production planning under uncertainty due to lack of homogeneity: proposal of a conceptual model
dc.creator.none.fl_str_mv Mundi, I.
Alemany Díaz, María Del Mar|||0000-0002-0992-8441
Poler, R.|||0000-0003-4475-6371
Fuertes-Miquel, Vicente S.|||0000-0003-3524-2555
author Mundi, I.
author_facet Mundi, I.
Alemany Díaz, María Del Mar|||0000-0002-0992-8441
Poler, R.|||0000-0003-4475-6371
Fuertes-Miquel, Vicente S.|||0000-0003-3524-2555
author_role author
author2 Alemany Díaz, María Del Mar|||0000-0002-0992-8441
Poler, R.|||0000-0003-4475-6371
Fuertes-Miquel, Vicente S.|||0000-0003-3524-2555
author2_role author
author
author
dc.contributor.none.fl_str_mv Departamento de Ingeniería Hidráulica y Medio Ambiente
Departamento de Organización de Empresas
Centro de Investigación en Gestión e Ingeniería de Producción
Escuela Técnica Superior de Ingeniería Industrial
Escuela Politécnica Superior de Alcoy
European Commission
Ministerio de Ciencia e Innovación
Repositorio Institucional de la Universitat Politècnica de València Riunet
dc.subject.none.fl_str_mv Planning
Optimisation
Production
Uncertainty
Mathematical modelling
ORGANIZACION DE EMPRESAS
MECANICA DE FLUIDOS
topic Planning
Optimisation
Production
Uncertainty
Mathematical modelling
ORGANIZACION DE EMPRESAS
MECANICA DE FLUIDOS
description [EN] Lack of homogeneity in the product (LHP) appears in some production processes that confer heterogeneity in the characteristics of the products obtained. Supply chains with this issue have to classify the product in different homogeneous subsets, whose quantity is uncertain during the production planning process. This paper proposes a generic framework for reviewing in a unified way the literature about production planning models dealing with LHP uncertainty. This analysis allows the identification of similarities among sectors to transfer solutions between them and gaps existing in the literature for further research. The results of the review show: (1) sectors affected by LHP inherent uncertainty, (2) the inherent LHP uncertainty types modelled, and (3) the approaches for modelling LHP uncertainty most widely employed. Finally, we suggest a conceptual model reflecting the aspects to be considered when modelling the production planning in sectors with LHP in an uncertain environment.
publishDate 2019
dc.date.none.fl_str_mv 2019
2019-01-01
dc.type.none.fl_str_mv journal article
http://purl.org/coar/resource_type/c_6501
VoR
http://purl.org/coar/version/c_970fb48d4fbd8a85
dc.type.openaire.fl_str_mv info:eu-repo/semantics/article
format article
dc.identifier.none.fl_str_mv https://riunet.upv.es/handle/10251/136500
url https://riunet.upv.es/handle/10251/136500
dc.language.none.fl_str_mv Inglés
eng
language_invalid_str_mv Inglés
language eng
dc.relation.none.fl_str_mv European Commission https://doi.org/10.13039/501100000780 H2020 691249 Enhancing and implementing Knowledge based ICT solutions within high Risk and Uncertain Conditions for Agriculture Production Systems
Ministerio de Ciencia e Innovación http://dx.doi.org/10.13039/501100004837 DPI2011-23597 METODOS Y MODELOS PARA LA PLANIFICACION DE OPERACIONES Y GESTION DE PEDIDOS EN CADENAS DE SUMINISTRO CARACTERIZADAS POR LA FALTA DE HOMOGENEIDAD EN EL PRODUCTO
dc.rights.none.fl_str_mv open access
http://purl.org/coar/access_right/c_abf2
Reserva de todos los derechos
http://rightsstatements.org/vocab/InC/1.0/
dc.rights.openaire.fl_str_mv info:eu-repo/semantics/openAccess
rights_invalid_str_mv open access
http://purl.org/coar/access_right/c_abf2
Reserva de todos los derechos
http://rightsstatements.org/vocab/InC/1.0/
eu_rights_str_mv openAccess
dc.format.none.fl_str_mv application/pdf
application/pdf
dc.publisher.none.fl_str_mv Taylor & Francis
publisher.none.fl_str_mv Taylor & Francis
dc.source.none.fl_str_mv reponame:RiuNet. Repositorio Institucional de la Universitat Politécnica de Valéncia
instname:Universitat Politècnica de València (UPV)
instname_str Universitat Politècnica de València (UPV)
reponame_str RiuNet. Repositorio Institucional de la Universitat Politécnica de Valéncia
collection RiuNet. Repositorio Institucional de la Universitat Politécnica de Valéncia
repository.name.fl_str_mv
repository.mail.fl_str_mv
_version_ 1869414110950588416
score 15,301603