Improving effectiveness of parallel machine scheduling with earliness and tardiness costs: A case study

This paper assesses the effectiveness in scheduling independent jobs with earliness/tardiness costs and variable setup times applying the Overall Equipment Effectiveness (OEE). The OEE is a common metric for measuring the manufacturing productivity. We defined a mixed-integer linear programming form...

ver descrição completa

Detalhes bibliográficos
Autores: Muñoz-Villamizar, A. (Andres)|||/items/b1fc45f8-fcea-40d9-9d1e-a5574a63d8b7, Santos-García, J. (Javier)|||/items/487cd61b-ac7c-4ca2-97c1-877209b2483d, Montoya-Torres, J. (Jairo)|||/items/ad28e282-2594-4fec-b00b-48b44a225e56, Álvarez-Sánchez-Arjona, M.J. (María Jesús)|||/items/2ecac6d4-1c44-4ab4-ba92-0faf2c5da62b
Tipo de documento: artigo
Data de publicação:2019
País:España
Recursos:Universidad de Navarra
Repositório:Dadun. Depósito Académico Digital de la Universidad de Navarra
Idioma:inglês
OAI Identifier:oai:dadun.unav.edu:10171/62720
Acesso em linha:https://hdl.handle.net/10171/62720
Access Level:Acceso aberto
Palavra-chave:Production scheduling
Earliness/tardiness
OEE
Optimization
Multi-objective
KPI’s
Descrição
Resumo:This paper assesses the effectiveness in scheduling independent jobs with earliness/tardiness costs and variable setup times applying the Overall Equipment Effectiveness (OEE). The OEE is a common metric for measuring the manufacturing productivity. We defined a mixed-integer linear programming formulation of the parallel machine scheduling problem with four different objective functions in order to compare different scheduling configurations. Real data, from a plastic container manufacturing company located in the Basque Country (Spain), were used to validate this approach. A sensitivity analysis was performed with different production capacities and earliness/tardiness costs in order to evaluate the trade-offs between economic performance (i.e., costs) and the partial rates of OEE (i.e., quality, performance and availability). The objective of this study is to propose a guideline to help management make decisions regarding the measurement and improvement of scheduling effectiveness through contemplating earliness, tardiness and variable setup times.