Estudio de alternativas para la optimización energética de una estación de bombeo de gran potencia (762 kW) con energía fotovoltaica en Picasssent (Valencia)
[EN] The objective of this study is to use the maximum possible of water from the Pinedo WWTP using a photovoltaic solar installation taking into account the existing infrastructure. In order to acomplish this objective, different options are proposed in the availability of water, in order to make t...
| Autor: | |
|---|---|
| Formato: | tesis de maestría |
| Fecha de publicación: | 2018 |
| País: | España |
| Recursos: | Universitat Politècnica de València (UPV) |
| Repositorio: | RiuNet. Repositorio Institucional de la Universitat Politécnica de Valéncia |
| Idioma: | español |
| OAI Identifier: | oai:riunet.upv.es:10251/114923 |
| Acesso em linha: | https://riunet.upv.es/handle/10251/114923 |
| Access Level: | acceso abierto |
| Palavra-chave: | Photovoltaic Optimize Batteries Optimitzar Bateries Solar EDAR Fotovoltaica Optimizar Baterías INGENIERIA HIDRAULICA Máster Universitario en Ingeniería de Caminos, Canales y Puertos-Màster Universitari en Enginyeria de Camins, Canals i Ports |
| Resumo: | [EN] The objective of this study is to use the maximum possible of water from the Pinedo WWTP using a photovoltaic solar installation taking into account the existing infrastructure. In order to acomplish this objective, different options are proposed in the availability of water, in order to make the most of the existing infrastructure, and with these availabilities they propose a series of alternatives to find the optimal size of the installation. Previously I studied the price per watt that would cost the installation, in order to compare alternatives and the possibility of adding batteries to disconnect from the network is studied. At the end of the study, it is concluded that maintaining maximum constant availability throughout the year is the best option, both environmentally and economically with the size of the optimized installation. |
|---|